Mission del Paso – El Paso Community College

El Paso Community College will accommodate future enrollment growth with the construction of a new 60,000 square foot building. This new facility on the Mission del Paso campus provides additional classroom space, offices, conference rooms, multipurpose space, science labs, support spaces, and a computer lab. It also includes a Flexitorium, a large, multi-purpose event and auditorium space. The Flexitorium will offer flexible seating arrangements and audio-visual equipment conducive to innovative teaching and special events.

CxGBS is providing Holistic Commissioning® of the HVAC, HVAC controls, lighting, lighting controls, and domestic hot water systems during the construction and warranty phases.

Added value through CxGBS® services:

CxGBS® identified several deficiencies in storefront assemblies and building waterproofing systems including the following:

  • Observed potential issues with accessibility to terminal units for maintenance and worked with team to determine best path to alleviate issue
  • Observed issue with change in size of framed duct chase that was different size than design. Worked with team to modify duct runs before installation of ductwork

TEAM:

Owner:
El Paso Community College

Design Professionals:
EXIGO Architects

Construction Professionals:
Flintco

Commissioning Professionals:
Commissioning & Green Building Solutions, Inc.